CS Wind: Doubling the Supply of Critical Equipment
One such project is in Pueblo, Colorado, where construction is underway on a nearly 900,000-square-foot expansion to the world’s largest manufacturing plant for onshore wind towers.
Under an engineer-procure-construct (EPC) contract, Burns & McDonnell is designing, building and assisting with environmental permitting on the eight-building complex for CS Wind. 1898 & Co. is also assisting CS Wind with siting additional wind turbines on its land to help power the facility. The South Korean-based company operates similar manufacturing sites in Europe, Asia and the Middle East.
The Pueblo plant supplies North American onshore wind developers with the massive steel towers upon which huge turbine blades are mounted. Nearly one in three wind turbine towers operating in North America were produced at the plant, which plans to meet future demand by doubling its production.
The existing plant’s central location in the middle of the U.S. next to a 140-year-old steel mill and two railroad lines is no accident.
“Pueblo is flush with skilled steelworker labor," says Bryan Allen, senior EPC project manager at Burns & McDonnell. Such labor is essential to an operation that is expected to add 850 new jobs to the local economy. Access to the Union Pacific and Burlington Northern Santa Fe rail lines is also important because tower construction is driven by transportation logistics.
“It takes three to five steel sections to create a tower to accommodate today’s taller, more powerful turbines,” Allen says. “Each section can be up to 36 meters long and weigh as much as 120 tons. That is as much as a rail car or tractor trailer can hold.”
The project's first phase involves construction of new production facilities to form and weld wind tower sections. The initial phase costs approximately $200 million and is slated for completion in 2025, with two more phases planned afterward. Burns & McDonnell also has a strategic alliance with CS Wind's newest acquisition, Bladt Industries, to provide steel foundation components for U.S. offshore wind projects.
South Fork Wind: Connecting Offshore Wind to the Onshore Grid
Manufacturing, transporting and installing the components for a new wind development — especially one built offshore — poses one set of challenges. Transmitting the power — again, especially from offshore to onshore — and injecting it into the electric power grid poses another.
Consider South Fork Wind, a new 132-megawatt (MW) offshore wind installation that's under construction off the coast of New York State. Built through a joint venture of Ørsted and Eversource Energy, New England's largest energy delivery company, South Fork is the first offshore wind installation supporting the state of New York. It began producing power in late 2023, when the first of its 12 turbines came online.
When fully operational, South Fork will generate enough renewable energy to power approximately 70,000 homes in New York. This power is brought onshore through a submarine cable that makes landfall in East Hampton. From there, it travels underground, crossing through seaside communities and paralleling the busy Long Island railroad before connecting to the New York state grid.
That 4.5-mile onshore journey presented complex design, construction and public engagement challenges, says Vinny Montemurro, project manager at Burns & McDonnell. Under a contract with Eversource, Burns & McDonnell served as the program manager responsible for executing the onshore portion of the project scope. Its team includes professionals in project management, construction management, community outreach and project controls.
The project was held to a wide array of compliance conditions during construction that dictated, for example, the protection and restoration of rare, threatened and endangered plant species as well as time-of-year construction conditions, Montemurro says. Engineers also took steps to increase grid reliability at the interconnection point where power from the offshore facility is delivered to the grid.
“You can build a wind farm and transport the power, but it will be turned off if the grid is full or unstable,” Storm says. In this case, the addition of a static synchronous compensator device is one of several design solutions helping to regulate voltage and enhance stability at the point of interconnection.
Applying Lessons From Experience
As U.S. offshore wind industry leaders look for ways to break the current development bottleneck, some are applying lessons learned in Europe and other places further down the renewable energy path.
“Right now, offshore developers in the U.S. are under pressure to purchase materials from local sources,” Appleton says. “States are learning that having their own complete supply chain is perhaps not the most cost-effective way of doing things. They’re discovering that a more collaborative regional or national approach might be more efficient.”
More standardization on permitting requirements and offshore wind farm design, Appleton says, could also help streamline development and reduce costs.
Onshore developers are also adapting their approaches to current market conditions. Flexibility is key, Storm says: “You don’t necessarily know what turbines and other equipment will be available when you’re ready to begin construction, so development designs must be flexible enough to accommodate different-sized platforms without incurring reengineering and permitting costs.”
More targeted approaches to site selection, due diligence and resource assessment are also critical, Storm says: “Screening potential development or interconnection sites for endangered species or permitting issues can help minimize the environmental concerns that might slow down a project.”