Meet Our Team

We are looking forward to participating in the 52nd annual exchange of ideas and experiences at the Transmission and Substation Design and Operation Symposium. Several Burns & McDonnell professionals will be among those sharing practical knowledge in Frisco, Texas.



Concrete Supply Options in Remote Locations for Transmission Lines and Substations

 Thursday, Sept. 5 | 9-9:45 a.m.

Regions of the United States that are favorable to renewable generation growth generally have sustained winds and sunny skies year-round. However, areas favorable to renewable generation are often found in remote locations with low population density and little infrastructure in place. Transmission providers tasked with connecting these generators to the grid often deal with the logistical challenges of constructing transmission lines and substations in remote locations. When a transmission line is constructed, engineers and constructors may find that the line traverses sparsely populated areas, sometimes hours away from concrete suppliers.

This presentation will focus on concrete supply in remote locations, as it can be a significant logistical hurdle to overcome. On the design and planning side, measures can be taken to help mitigate these logistical challenges. For construction, there are several concrete supply options that can be considered.

Copresenting with Vincent Carriger, construction manager, Lower Colorado River Authority.

Travis Layton
Section Manager
Nate Schrein
Senior Civil Engineer


Reconductoring and Associated Lattice Tower Foundation Analysis and Modifications

 Thursday, Sept. 5 | 3:30-4 p.m.

In 2016, FirstEnergy (FE) initiated work to replace conductor and convert existing overhead ground wire to OPGW on three 69-kV circuits in Pennsylvania. The project included 26 circuit miles of lattice towers and posed many challenges, including an accelerated schedule, outage constraints, difficult access and the lack of existing lattice tower foundation capacity drawings. During the design phase of the project, it was discovered the NESC 250C Extreme Wind loading case was causing uplift capacity issues on existing lattice tower foundations. FE, with the assistance of Burns & McDonnell, completed a ground line reaction comparison of the existing configuration against the proposed design loading and identified each tower location where the new loading would exceed the existing configuration’s ground line reactions. The companies analyzed grillage capacities on 41 lattice towers representing five different tower types. Grillage capacities were developed for these specific towers by following industry design practices. A geotechnical investigation was completed to characterize the native soil and backfill properties at the tower locations. The analysis showed the proposed loading increase would result in several of the grillages having insufficient uplift capacity. The factored capacities were compared with the extreme load case and used to determine which structure foundations required modifications to provide adequate uplift resistance.

Several mitigation options were developed to provide additional capacity to the existing foundations. The feasibility of each option was evaluated by representatives from engineering, construction, project management, real estate and transmission maintenance. Options were assessed and ranked considering cost, constructability, rights of existing easement agreements, aesthetics, landowner impacts, and long-term performance and maintenance. The uplift mitigation system included a bracket designed to attach to the existing tower leg near the ground that can accommodate connection to multiple anchor types.

The attachment design had to account for induced stresses on the tower leg, additional bracing and reinforcement, and constructability to properly install the anchors adjacent to the tower leg and foundation while securing the anchor to the bracket. The structural design of the attachment bracket required close coordination with construction, project management, real estate and geotechnical engineering. Several anchor systems were utilized to overcome varying rock depths and soil profiles. These anchor systems included grouted threaded rod rock anchors, helical anchors, stingray earth anchors and a hollow bar injection anchor system.

Copresenting with Tom Guess and Jon Trout, FirstEnergy.

Brett Fisher
Senior Transmission Engineer
Paul Barker
Senior Geotechnical Engineer