Understanding Utility Constraints
With early utility engagement, a typical carbon capture and compression project takes two or more years to complete using an engineer-procure-construct (EPC) approach. Bringing a utility to the table later in the process can extend this timetable significantly. It can take months for a utility to plan and implement substation improvements or other needed upgrades — presuming it has the capabilities to do so. If not, those upgrades may be added to the ethanol, ammonia or other processing facility’s own scope of work.
Consider that the rural electric distribution systems that supply many processing facilities operate distribution-level substations ranging from 12.47-kV to 34.5-kV. These utilities often own the distribution system all the way into smaller facilities’ switchgear. Operating loads for these processing facilities are typically 10 megawatts (MW) or less, with some less than 5 MW.
The utility distribution substations feeding these facilities may also have relatively weak power systems because of their low short-circuit capability. This electrical infrastructure is insufficient to power the high-horsepower compressors, pumps and fans in carbon capture and compression projects. Utility upgrades may be necessary to provide the starting torque or starting power needed to start these compressors. While the power supply does not directly influence the performance of carbon capture processes, it must be reliable and adequate for the demand created by carbon capture equipment.
Early engagement with utilities can enable solutions to these challenges. Discussion topics can include everything from transmission line and substation capacity to feeder availability, voltage dip limits and power factor requirements, land acquisitions, partnerships and more. Conversations can prove fruitful as parties negotiate utility contracts based on power demand, energy consumption and service voltage for the new facility. These discussions can commence as soon as the industrial facility has identified its conceptual compressor size and motor data, two factors that are necessary to determine substation capacity requirements.