Consult Early and Communicate Regularly
The process for obtaining FERC approval can take up to two years, depending on the size and scope of the project. The chances of streamlining this process improve if it can be demonstrated to a FERC project manager that regulators have been engaged from the start. That usually involves determining each regulatory agency’s expectations as well as outlining the applicant and the project’s expectations of each agency.
Identify and contact agencies as soon as there is a clear need for a project. In addition to FERC, those agencies could include the U.S. Army Corps of Engineers, U.S. Fish and Wildlife Service, Bureau of Land Management, state historic preservation agencies, state environmental agencies and other groups, depending on the project location. Outline a plan to file for a certificate and provide a general timeline for construction to each group.
Ongoing communication with FERC is valuable, particularly during the prefiling phase of a project. During this period, FERC staff can provide feedback on draft plans, including informal advice on additional data that may be needed. Staff may also share comments from landowners or agencies about draft plans and suggest how they be addressed in the final application. A FERC project manager is often an effective source of guidance for moving the project along. After the application is filed, contact with FERC personnel becomes more formal due to the commission’s ex parte rules.