A Systems Approach to Project Success
Whether a plant uses a gas-fired aeroderivative simple-cycle or an advanced gas turbine combined-cycle, it will use thousands of unique electrical and mechanical components. Coupled with the many personnel and disciplines required to construct a plant — and the need to get them online faster — large power projects are naturally complex.
As commissioning and turnover dates draw near, many large projects can run over budget and late on schedule. Crowded workfronts on project sites, colliding schedule timelines and expectations for speedy completion compound an already challenging project environment.
The key to achieving success in complex construction projects rests with viewing the plant as many smaller operating systems. Using a systems approach to planning then helps project teams understand the completion of individual systems to reach each critical commissioning milestone.
It is critical for the project engineering and construction teams to buy into the overall system commissioning plan. Development of the initial commissioning plan sets project procurement deliverables, major construction award dates and individual system turnover scope. The plan needs to be coordinated with the construction, engineering and procurement teams, and must align with the construction plan to build the power plant.
The commissioning schedule and system turnover plan is just the first step in creating a successful project. Managing the project to achieve each of the hundreds of small milestones then becomes the primary challenge.
In the past, reporting on actual project completion progress has been a challenge due to the reliance on inaccurate completion metrics and overpromised early construction progress. Inaccurate time projections and working hours to finish the construction activities have also contributed to the problem. Incorporating effective technology to track the commissioning and turnover process helps minimize and mitigate these issues.
Project Plan Design
The design phase focuses on each process system, building structure or electrical system of a project.
In upfront Level 1 project planning, startup and commissioning should be considered as an integral part when defining and incorporating project components. Including startup and commissioning development at the onset of planning provides critical late-stage tasks planned early to identify and coordinate requirements, potential challenges and areas of possible inefficiency.
Commissioning professionals must be engaged during the engineering phase, developing the scope of turnover documentation, working with design professionals to develop the flushing plans, testing plans and detailed component lists that make up each system to accomplish those plans. Commissioning professionals should also be reviewing the process piping isometric diagrams, and one-line and three-line diagrams, to confirm the pipe routing. Electrical configuration will allow efficient flushing and testing.
Incorporating planning for commissioning during the early planning phase of the project greatly improves the potential for successful turnover.
Project Procurement
Procurement professionals work with the engineers to specify, design and schedule all major equipment required for a project. Construction professionals must then work with procurement to sequence the delivery of equipment to coincide with plant construction to allow for efficient construction activities.