Utilities with perfect drawings of their facilities are few and far between; there are almost always some discrepancies. Using the open-book approach gave Beaches Energy Services additional clarity on any changes of scope based on differences from drawings. A contingency amount was built into the prime contract to compensate for any additional scope arising outside of the contractor’s fault.
The project similarly benefited from having a Burns & McDonnell construction superintendent with more than 30 years of experience on-site to monitor construction and mitigate any potential shortcuts, since quality was a critical factor for the utility and Burns & McDonnell.
As part of efforts to lower risk and plan project sequencing effectively, the prime contractor brought in contractors prior to setting prices and shared the 30% design and what was to be built. In those meetings, the engineering team and subcontractors brainstormed how to achieve the objectives with minimal outages, and how to design and sequence the construction for a combination of safety and efficiency. These open discussions helped deliver schedule certainty, which was reinforced by having the construction superintendent monitoring safety and quality and seeing that the project schedule was being met.
The EPC prime contractor met with subcontractors weekly to provide a three-week look-ahead and discuss any issues or upcoming outages. Any plan discrepancies or changes, such as potentially rerouting a conduit, would be discussed. The prime contractor also met biweekly with the utility to provide ongoing status updates and discuss any significant issues without forcing the utility to delve into the fine details of the work.
In addition to installation and energization of Autotransformer No. 2 at the substation, the project included addition of a 138-kV station service voltage transformer (SSVT) connected to the 138-kV ring bus, providing a measure of redundancy. Five motor-operated disconnect switches were replaced as well, among the many pieces of equipment being changed out. The switches had been previously ordered and were awaiting installation, but the project team discovered that a few accessory parts were missing. The probability is high that such a detail could have been overlooked by strained internal resources, but the EPC team was able to get the parts expedited as soon as the issue was identified. If not for this project, the problem likely would have come up in the middle of an outage, forcing the utility to place an order through regular procurement and costing precious time. Instead, the project delivery structure helped obtain the necessary parts a day before the outage, resulting in no negative impact to the project schedule.