To better understand the existing grid infrastructure at the proposed point of interconnection for new power projects, preliminary grid assessments can be performed that replicate the CENACE process, providing a decision gate for viable project locations before requesting a formal interconnection study through CENACE. External Trusted Users (Usuarios Externos de Confianza) of CENACE’s Market Information System, including Burns & McDonnell, have access to CENACE’s transmission system and load growth models, which makes it possible to perform an indicative study similar to CENACE.
The interconnection application process centers on system reliability. Client parameters, such as size and location, can be entered into the model to identify system reliability impacts and potential mitigation requirements. This simulates what the CENACE indicative study results might look like, enabling clients to winnow their applications to those with fewer costs associated with impacts outside of the project fence. However, it is important to note that CENACE models are posted as of a specific point in time. Developers should also consider generation within the CENACE queue that could impact power flow in the future, as well as transmission facility rating assumptions.
Mitigate Risk
Preliminary grid assessments can reduce cost and schedule risk throughout the CENACE process by avoiding submission of project studies that would trigger high system upgrade costs and by enabling proactive responses to time-sensitive study findings. Beyond interconnection impacts, developers of new power projects should also factor in present or future congestion and other costs associated with delivery of power to the end user. These are questions we can help address as a registered trusted user with access to the Market Information System’s power flow and market models.
Focus Investments
Often, developers investigate and select multiple development sites based on resource and land availability, but don’t consider the availability of grid infrastructure until CENACE defines it during the interconnection process. However, preparing, submitting, monitoring, and responding to multiple interconnection applications is extremely labor intensive. The pre-indicative study helps developers converge on a single site with the optimal opportunity and lowest cost to pursue.
Maintain Flexibility
Due to the parallel nature of the three major site selection factors, developers can benefit from the flexibility of understanding grid interconnection information from pre-indicative studies before committing to the interconnection application schedule determined by CENACE. Obtaining this level of information on a developer’s own time without looming response deadlines can allow better analysis and planning for unexpected required upgrades. For example, Criterion 43 of the Interconnection Criteria Document says that an interconnection agreement must be signed 25 days after receiving the results of the facilities study.
Developers can also avoid penalties from CENACE for changes to their interconnection application. For example, increasing project capacity by less than 10 percent requires CENACE to perform a sensitivity analysis, delaying the interconnection process. A change of more than 10 percent requires a completely new application. Renewable energy clients are often interested in finding the maximum available injection capacity for a point of interconnection because of available wind and solar resources and additional nearby land available for purchase. Understanding this information before commencing the interconnection process can reduce change penalties and take advantage of grid availability and economies of scale.
Increase Control and Understanding
Soliciting a pre-indicative study gives developers a degree of control over the study depth and assumptions. Developers often conduct internal investigations of site feasibility to some level. Working privately with a development consultant can make sure these preliminary investigations are utilized. For example, developers might have more market intel on other nearby energy projects in the interconnection queue, compared to the public data available from CENACE.
Additionally, the explanation of pre-indicative study results can be referenced and used as a defense against mismatching results during CENACE’s interconnection studies. Section 9.1.8 of the Interconnection Manual says that CENACE may consider the opinion of the applicant if other technical solutions constitute lower costs.