Project Execution and Innovation
One of 38 projects funded by the EPA at the time it was started, the Northwest Water Facility utilized a progressive design-build delivery process for increased adaptability. Because of funding requirements, the project team had to move quickly. WIFIA funding defers payments for five years from the loan approval date, so starting on time was essential in order to maintain financing benefits.
In order to meet the schedule demands, the project team right-sized design packages and worked with the state regulatory agency, the Kansas Department of Health and Environment, to expedite construction. While other projects around the country were significantly impacted by the pandemic, the Wichita team was able to overcome supply chain challenges and circumvent labor shortages by expediting early procurement of long-lead equipment and maintaining continuity of work for the local labor force. To maintain warranty and reduce exposure to the elements, the site team constructed an on-site warehouse for storage of major components until they were needed to protect the equipment while minimizing potential delays to the project.
The design incorporated 24 hours of water storage capacity, along with a pump station that connected to existing and planned distribution networks. Additional on-site power solutions, including backup generators, were included to support operations during outages and extreme weather events. In total, the project required more than 450,000 cubic yards of earthwork, more than 18 million pounds of reinforced steel and over 1.5 million labor hours.
Because redundancy is an important component of the plant’s resiliency, over 17 miles of process piping is included in the design. This feature helps eliminate any single point of failure and facilitates simultaneous treatment of groundwater and surface water sources. The clarifier complex, which spans the size of four football fields, also has added redundancy and includes six clarifiers, each with a capacity of more than two million gallons, making them some of the largest in the country.
Complementing this is the two-level filtering complex, featuring 16 filters that treat five gallons per minute per square foot, designed with a depth that exceeds current requirements and offers room for potential future biofiltration capabilities. Additionally, the chlorine contact basin is equipped with significant valving, providing maximum operational flexibility and full-capacity redundancy.
Results
The Northwest Water Facility — officially renamed Wichita Water Works — was completed on time and under budget. Its nearly $500 million price tag stands as the single largest capital investment in Wichita’s history. While it is a substantial sum, it represents a big win for the city. By maintaining schedule discipline throughout this multiyear project, the team will prevent $93 million in interest and cost escalation for water ratepayers. These savings have been calculated by the EPA, based on the combination of early cost certainty and a 1.17% interest rate through WIFIA.
The project generated $2 billion in local economic benefits, with 77% of contracted dollars remaining local to Wichita and over 12% going to minority-owned, woman-owned and disadvantaged businesses. In an effort to help buoy the construction labor market in the city, one highlight of the project was the collaboration with Wichita State Tech on an apprenticeship program that will contribute positively to the long-term development of the community’s workforce. As a result of this project, Burns & McDonnell helped grow the city’s emerging business enterprise capacity, leaving a lasting impact on the local business community.
The Northwest Water Facility is part of a decades-long plan to make Wichita more resilient to drought and other extreme conditions. With this new facility, Wichita is positioned to provide the city and surrounding area with a sustainable, flexible water supply for decades to come.