Solution
On the main site, we performed high-resolution site characterization, including usage of environmental sequence stratigraphy (ESS), TarGOST/electrical conductivity/hydraulic profiling tool probes, geochemical analysis, microbial population quantification and nested monitoring wells, combined with conventional soil and groundwater sampling. Most impacts were present in more permeable glacial outwash sands located approximately 20 to 35 feet below the ground surface.
The Illinois Environmental Protection Agency had approved conducting a pilot study to evaluate the effectiveness of in-situ remedies for implementation at the site shortly before the utility learned about the school development. The pilot study was designed as an alternative to remedy source material impacts that would be less disruptive to the community. The approach used a combination of surfactant-enhanced product recovery and in-situ chemical oxidation. Soil, groundwater and soil gas data were collected for several months after the pilot study to confirm the effectiveness of the combined approach.
While the pilot study activities were ongoing, the project team began rapid investigation of the adjacent school property to evaluate potential soil, groundwater and vapor intrusion risks. Following the results of that investigation, the utility was able to issue a request for proposal for the excavation and engineered barrier installation to meet residential remedial objectives.
Efforts to expedite the school property remedy included pre-excavation confirmation sampling, submission of expedited in-situ stabilization treatability samples prior to awarding the contract, and early and frequent involvement of the school development property stakeholders to align remediation design details with property development requirements. Burns & McDonnell prepared the design documents, assisted in bidder selection, conducted air monitoring and served as owner’s engineer during the remedy implementation on that parcel.
Remediation on the main site was conducted using a combination of in-situ treatment technologies and excavation and off-site disposal. Despite early initiation of utility relocations, some elements such as existing sewers, utility poles and other subsurface utilities presented significant challenges for conventional excavation.
Full-scale remedy implementation began in December 2022 with installation of 34 injection/extraction wells. The surfactant enhanced product recovery (SEPR) phase operated from February-August 2023, and the in-situ chemical oxidation (ISCO) injection phase delivering iron-activated sodium persulfate via more than 200 direct-push injection locations operated from May-August 2023. Overlap between the SEPR and ISCO phases was required to meet the project deadline. The overlap was coordinated using a variety of factors, including property-specific schedule considerations and mass-flux recovery criteria updated using daily collected performance monitoring data.