SOLUTION
The $5.8 million project called for our team to develop an adaptive site management approach to integrate soil remediation under the RCA process with demolition of the facility.
Our team prepared and submitted a Pre-Demolition Characterization Work Plan to the EPA and Nebraska Department of Environmental Quality (NDEQ) to obtain the data needed to refine schedule and budget criteria. By collecting soil samples from beneath the buildings, we determined the presence and extent of the contamination. We used these findings to estimate the amount of soil to be removed and determine appropriate disposal methods.
Using the data collected during the Pre-Demolition Characterization activities, our team developed a Soil Treatment Work Plan proposing treatment on-site during excavation activities.
The integrated team met with regulatory agencies to conceptualize a rapid remediation method that complied with the RCA framework. Working together, we received approval to implement an on-site treatment method that involved mixing the metals-contaminated soil with Portland cement. Soil treatment bench tests were performed to confirm the feasibility of stabilizing metals in the soil to below toxicity characteristic leaching procedure (TCLP) regulatory levels. This method stabilized soil at the site rapidly and allowed us to dispose of soils as nonhazardous waste.
Ongoing meetings and frequent communication with regulators prior to and during the preparation of the work plans resulted in regulatory approval within six weeks. Implementation began immediately thereafter.
By the time the project was complete, our team had excavated, treated and disposed of 8,961 tons of stabilized soil, along with removing and disposing of 100 tons of fertilizer solids as hazardous waste, 375 tons of demolition debris and 94 loads of concrete. When restoring the site for redevelopment, we rubblized 7,160 tons of concrete slabs and foundations for reuse as backfill for soil excavation.
Overall success was based in the EPC project delivery method, which assigned us overall project management and budget and schedule control, from concept and design to procurement and construction. This approach made it possible to conduct environmental investigations during the demolition process and to integrate demolition and remediation decision-making. Agile work plans allowed decisions to be made in the field in real time, providing flexibility to accommodate time and budget constraints.