Burns & McDonnell implemented a phased approach using focused shutdowns, with outages ranging from three days to three weeks. These planned outages allowed the team to complete intensive work in short, defined time frames while minimizing disruption to ongoing, active operations.
First off, the team identified an adjacent area for construction of the first new production line. Once the new line was installed — all while the existing equipment kept running — the new line was commissioned and put into production. This then allowed for removal of legacy equipment, to make way for the second new production line — work that also was completed while the second legacy line remained in production. Following installation of the second new system, a brief, carefully planned shutdown enabled the integration and activation of this new production line. With both upgrades complete and operational, the remaining obsolete equipment was removed, providing a seamless transition to enhanced production capabilities. Once both new lines were up and running, the remainder of the legacy equipment then could be removed.
Modern conveyor and packaging systems were also integrated to further enhance efficiency. Through early and detailed planning, procurement timelines were carefully synchronized with construction activities. Given the extended lead times for certain systems, proactive coordination was essential to prevent delays and see through a smooth, uninterrupted upgrade process. The upgrades encompassed renovation of approximately 12 packaging distribution lines and installation of a dozen new process equipment systems for each production line — with a total of about 100 pieces of processing and packaging equipment across both production lines — to significantly enhance both operational capacity and efficiency.
Additionally, a major environmental retrofit converted a standard process space into a refrigerated environment, maintaining precise conditions at 40° F and 20% relative humidity. This transformation was critical in extending production windows between sanitation cycles.
To support temperature control improvements, the team installed five new critical air processing rooftop units, each weighing approximately 21 tons, along with 90 tons of rooftop steel and 12-ton heat exchangers. Each of the critical air units arrived in three separate pieces. The pieces were then craned into place and then connected once they were placed on the roof. These units, along with the heat exchangers and extensive steel infrastructure (180 tons overall), were integral to achieving the controlled process environment and providing heat to the production equipment. The team also conducted equipment inspections and readiness reviews before each shutdown to see that all systems met the required specifications.
Risk mitigation measures included physical barriers to control movement within the facility, carefully designated entry and exit paths for personnel and materials, maintaining negative air pressure within the construction zones to manage dust and fume control and constant inspections of barriers and contaminant control to maintain product quality and safety. At peak, there were more than 120 personnel onsite during the day shift and around 80 during the night shift.