Challenge
With the global supply chain facing unprecedented instability in 2021 and 2022, the project team faced significant challenges in equipment delivery delays throughout the project’s duration. Most notably, the medium-voltage switchgear for the project arrived on-site nearly six months late. During this delay, Burns & McDonnell conducted thorough and persistent vendor surveillance consisting of daily meetings and weekly visits to factories in order to provide Wisconsin Public Service with clear and accurate information about the status of the equipment fabrication, forecasted delivery and the delay impacts to the project.
A detailed work plan was pulled together on-site to see that the switchgear was set and built out, and cables pulled and termed, as safely and quickly as possible. The work was planned for two months and was completed in one due to the efficiencies identified in planning and added night shift work.
Additionally, the project team had to react quickly during commissioning when it was discovered that cooling piping for the project was routed incorrectly. Similar to a car engine, a RICE unit has cooling water piping routed to radiators: Water from the engines comes in, is cooled and goes back out to the engine. But in this case, what the original equipment manufacturer provided was flipped: The supply was routed to the return and the return was routed to the supply.