While the design for the new scale house met the client’s needs, it also would pose challenges for any construction crew. Working together, the design and construction teams addressed multiple factors when developing the conceptual design, construction and schedule for the new facility.
The new scale house needed to be compact, yet it still required HVAC, electrical, plumbing, networking and other technologies and services used in larger buildings. The new HERC building — measuring just 12 feet by 24 feet — allows one or, at most, two operators to transition quickly between inbound and outbound trucks passing over the scales. In order to efficiently complete construction of such a compact building, the schedule needed to accommodate a lean construction team, as only three construction workers could work inside the building at a time.
The new building required other unique design features. It has windows and television monitors located at nonstandard heights and positions that optimize the visibility of trucks passing through. The new scale house also required additional building permit approvals because the facility needed to be slightly larger than the one it would be replacing. The wheelchair ramp length necessary for Americans with Disabilities Act (ADA) compliance exceeded the space available, so variances were needed before work could begin.
SOLUTION
Designing and planning for the new scale house began six months before the outage was scheduled to begin. Working with the general contractor and its subcontractors, we plotted a work plan for phased construction so that the replacement scale house would be constructed and ready for service in time for the planned outage. Ongoing meetings and frequent communications prior to and during the project preparation aided the team in receiving owner and permitting approvals two months prior to construction. Multiple preconstruction meetings were conducted with subcontractors to help confirm everyone was prepared to execute the detailed plans on schedule.
The team also constructed the basic new structure at an off-site location to later transport to the HERC. Traffic, parking and other logistical considerations helped to guide decision-making on transportation as well as identification of building components to be prefabricated.
To complete the foundations by the end of the first week, the team demolished the existing scale house in the first two days of the outage and then poured fast-setting concrete for the new building’s footings. As the second week began, the new framed building was hoisted into place with a crane. In one day, the building was set into place by carefully aligning and welding its metal frame to preset metal anchors in the footings. And finally, with five working days left, the team set the windows, fastened the drywall and completed the interior finishes.
RESULTS
With a tightly coordinated outage schedule, the new scale house was completed within the two-week planned outage, without causing any disruptions to other renovation and maintenance activities at the site. The new scale house contributes to Hennepin County's zero waste goal by allowing the HERC to continue waste-to-energy processes, resulting in a 90% reduction of waste volume.