Results
The new double-circuit 230-kV transmission line segment was placed in service on schedule in May 2022, two years after construction began.
Proactive outreach efforts enabled an early permit scenario to be realized for the environmental permits and certification of public convenience and necessity (CPCN) order, reducing the overall cost for BGE and its customers. The outreach also helped guide the selection of an approach that minimized impacts for the region while achieving the necessary improvements for system reliability.
The project created several positive economic impacts for the regional economy. Construction was performed by a local marine construction contractor with waterside facilities close at hand in Curtis Bay. Additionally, 8,200 cubic yards of concrete were provided by a local diverse batch plant and 1,110 tons of rebar were installed by a diverse specialty subcontractor.
Towers 3 and 4 are currently the tallest transmission monopoles on the continent, standing 397 feet above the river. The use of high-strength, low-sag conductor allowed the monopole heights to be minimized while maintaining channel clearance for ship navigation.